Skip to main content

Production Order in SAP: CO01, MD16, CO02, CO15

 A production order defines which material is to be processed, at which location, and at what time and how much quantity is required. It also defines which components and sequence of operations are to be used and how the order costs are to be settled.

  • Planned orders are results of running MRP. Shortages of materials that are set to internal procurement will create planned orders, which can be converted into production orders. Production orders are “hard copies”; they cannot be adjusted by an MRP run anymore.
  • BOM and routing data of the materials are copied into the production order which determines the list of components and operational data in the order.
  • Planned Costs also gets updated in the production order via component price and routing activity price.
  • You can run an availability check on production orders which determines any missing components in the order so that you can bring that missing component for the order execution at shop floor.
  • You can print the production order for shop floor which indicates the list of components to be consumed and what kind of operations to be performed in sequence at the work center.
  • After you have physically produced the material, you can declare the production through order confirmation which updates the activities cost such as machine running price, labor price on the order.
  • You can decide to automatically do the backflush (consumption) of components during order confirmation according to the BOM. The consumption will reduce the inventory of components and it is carried out with movement type 261 in SAP.
  • You can also post goods receipt of the material automatically during order confirmation. Goods receipt would increase the inventory of the material, and it is carried out with movement type 101 in SAP.
  • After Order Confirmation, all the cost such as the cost of components and activity cost will be debited on the order, and once you post goods receipt, costs will be credited on the order.
  • Once, production order is fully confirmed and delivered, or business has decided not to execute that order, then it needs to be technically closed which means order will no longer be considered in MRP run and will be deleted from stock/requirement list. Order reservation on components will also be deleted.

How to Create and release Production Order

Production Order creation is required to produce the material and consume the components which are used, and it also specifies the sequence of operations to be performed at the work center.

The release of order signifies that the order is ready to be executed at the shop floor. You can do an automatic release of order also during creation mode by using relevant production scheduling profile in the material master with auto release indicator set.


Step 1) From SAP Easy access screen open transaction CO01

  1. Enter the material code for which production order needs to be created.
  1. Enter Plant Code.

Production Order in SAP: CO01, MD16, CO02, CO15


After filling in all the fields, clickProduction Order in SAP: CO01, MD16, CO02, CO15 or press Enter to go to the next screen.

Step 2) In this Screen

  1. Input the order quantity.
  1. Select the option”current date” in scheduling sub-screen.

Production Order in SAP: CO01, MD16, CO02, CO15


After filling the entire fields press click Production Order in SAP: CO01, MD16, CO02, CO15to confirm, the system will then copy BOM and Routing data in the order.


Step 3) In the same screen,

  1. Click Production Order in SAP: CO01, MD16, CO02, CO15 to release the order. The following message will appear in the bottom left corner:Production Order in SAP: CO01, MD16, CO02, CO15.
  1. ClickProduction Order in SAP: CO01, MD16, CO02, CO15 to check material availability. The system will show the message regarding the availability of components.

Note: You can also decide not to release the order if there are missing parts found in availability checks.


Production Order in SAP: CO01, MD16, CO02, CO15


Click button Production Order in SAP: CO01, MD16, CO02, CO15 to save, the following message will show in the bottom left corner: Production Order in SAP: CO01, MD16, CO02, CO15.


How to Create Production Order by converting Planned Order

Planned orders are the result of MRP run and should be converted to production order for further execution process.

You cannot directly declare production using planned orders and, therefore, it needs to be converted to Production Order.

Once, planned order is converted to production order, planned order gets deleted from the system and is no longer available to be considered in MRP (Material Requirement Planning).


Step 1) From SAP Easy access screen open transaction MD16

  1. Select radio button “MRP controller” from the list, which is a group of materials.
  1. Press right mark sign on top or press enter from your keyboard.

Production Order in SAP: CO01, MD16, CO02, CO15


The system will show the screen as below.


Step 2) In this screen, we will fetch the planned orders based on MRP controller and selection dates.

  1. Enter plant code.
  1. Enter MRP controller
  1. Enter end selection date till all planned orders will be extracted.

Production Order in SAP: CO01, MD16, CO02, CO15


Click right mark sign from the bottom or enter from the keyboard to move to the next screen.


Step 3)In this screen,

  1. Select the grid for which you want to convert the planned orders
  1. Press “convert to production order” button for the conversion.

    Production Order in SAP: CO01, MD16, CO02, CO15




Production orders will be created after conversion of planned orders.

How to Change production Order

You might require to change production order incase if your business wants to change some planning quantity or if BOM/Routing has been changed after the order has already been created.

Step 1) From SAP Easy access screen open transaction CO02

  1. Enter production order number which you want to modify.

Production Order in SAP: CO01, MD16, CO02, CO15


In the same window you can see “Display Overview” button is selected, it is selected by default.

After filling in all the fields, click Production Order in SAP: CO01, MD16, CO02, CO15 to go to the next screen.

Step 2) In this screen, the order will be modified.

  1. Change the Order quantity to 9000 or whatever your requirement is as shown below.

Production Order in SAP: CO01, MD16, CO02, CO15


After finishing all modifications, click button Production Order in SAP: CO01, MD16, CO02, CO15 to save the order. The system will show a message like Production Order in SAP: CO01, MD16, CO02, CO15Order number saved 6600000887 at the lower left corner.


How to confirm production order

Step 1) From SAP Easy access screen open transaction CO15, three activities occur at the same time with confirmation.

  1. Generate confirmation document
  2. Consume raw materials or semi-finished goods
  3. Good receipt of finished goods or semi-finished goods
  1. Enter Production order number

Production Order in SAP: CO01, MD16, CO02, CO15



After filling in all the fields, click Production Order in SAP: CO01, MD16, CO02, CO15 to go to the next screen

Step 2) In this screen, we will enter the actual yield quantity to be confirmed.

  1. Enter the yield quantity which is the produced quantity you want to declare
  1. Press Goods Movement button at the top to check the automatic goods movement happening along with confirmation

Production Order in SAP: CO01, MD16, CO02, CO15


Step 3) In this screen, you will see the goods receipt of parent material and goods issue of components.

If the control key of the last operation in the order specifies automatic goods receipt, the system automatically posts the produced material to unrestricted stock.

Automatic goods receipt can also be activated by the production scheduling profile in the material masterwork scheduling view.

If you confirm an order with components that have the Backflushing indicator set in the material master MRP1 view, the system automatically posts a goods issue (GI) for these components.


  1. Auto Goods receipt (GR), production of material carried out using movement type 101.
  1. Auto Goods issue (GI), consumption of components carried out using movement type 261.

Production Order in SAP: CO01, MD16, CO02, CO15


Click buttonProduction Order in SAP: CO01, MD16, CO02, CO15 to save.

The system will show a message likeProduction Order in SAP: CO01, MD16, CO02, CO15 at the lower left corner, to hint how many goods movement are posted successfully or failure.

Failed goods movements due to a deficit of stock for consumption are reprocessed manually.


How to TECO (technically complete) production order

Technical completion of the order is required when production order is either fully delivered, or it is not to be processed further at shop floor.

After technical completion order status changes to TECO, no further goods movement can be done against the order.

Order is no longer available in MRP run and gets deleted from stock/requirement list.

The controlling department can then carry out the variance calculation on the production Order after TECO status.

Step 1) From SAP easy access, open transaction CO02

  1. Enter the order number which you want to TECO.

Production Order in SAP: CO01, MD16, CO02, CO15


ClickProduction Order in SAP: CO01, MD16, CO02, CO15 to next screen after filling all fields,

Step 2) In this screen, we will see how to place production order to TECO status,

  1. Click in menu Function-> Restrict processing ->complete technically System will show message in status- TECO

Production Order in SAP: CO01, MD16, CO02, CO15

  1. System will show message in status- TECO

Production Order in SAP: CO01, MD16, CO02, CO15



Troubleshooting

  • BOM and Routing must exist before creation of production order else it will not be copied into the production order and can cause issues in planned costs updation and consumption of components during confirmation process thereby impacting the inventory of the components.
  • Production order must be released before doing order confirmation as the released status of the order allows confirmation to happen.
  • If you receive any Accounting error during goods movement in the confirmation process, then ensure the right valuation class is set in the material master Accounting view or contact Finance team.
  • Ensure that standard cost for the material is updated to avoid any costing related errors such as activity price missing etc. during production order confirmation.
  • If some goods movement gets failed during confirmation process due to the stock deficit, then you should process them separately once components are brought to stock.

Comments

Popular posts from this blog

How to Create Production version in SAP PP C223

  The production version is the link between a product BOM (Bill of Material) and the process Routing. It determines which alternative BOM is used together with which routing to produce a material or plan a material. There may be different production versions based on the lot sizes and validity dates. For example, there may be different versions if you want to produce 1 – 100 liter of paint than 100 – 1000 liter of paint, as such the different composition of BOM may be required in both cases. It comprises of the following data: The assignment of routings to the production version The assignment of the alternative BOM to the production version Production versions are used in material requirements planning (MRP), production order creation, and product costing to select the most suitable routing and the corresponding bill of material. In order to create production version, perform the following steps- Step 1)  From SAP Easy access screen open transaction  C223 Enter Plant Co...

Bill of Material (BoM) in SAP PP: Create, Change, Display

  What is Bill of Material (BOM) and its role? A bill of material is a complete, formally structured list of the components that make up a product or assembly. The list comprises of the material number of each component, together with the quantity and unit of measure. BOM can be single level and multi-level. For example, finished material would contain semi-finished materials as components which in turn would contain raw materials as components in next level. There can be different alternative BOMs for a product depending upon the lot sizes, validity dates, and different production methods. BOM is used in production planning for semi-finished and purchase planning for raw materials. BOM’s are also used in standard cost calculation for finished Product by rolling up the cost from raw to semi-finish and then to finished Product. Material BOM can be made for material in PP module and equipment BOM are used in Plant Maintenance module. How to create BOM Step 1)  From SAP Easy acce...

Introduction to SAP PP (Production Planning)

  What is Production Planning? Production Planning is the process of aligning demand with manufacturing capacity to create production and procurement schedules for finished products and component materials. SAP PP is an important module of SAP. It tracks and makes a record of the manufacturing process flows, for example, the planned and actual costs. Also, goods movements from the conversion of raw material to semi-finished goods. It is fully integrated with the other SAP modules: SD, MM, QM, FICO & PM. Organization Structure in SAP PP In any live Production Planning module, locations of manufacturing plants and storage within the plants, should be available in the system. Importance of Plant and storage locations in Production Planning- All Production master data is created at Plant level. Planning activities are also performed at Plant level. Production Confirmation process and related goods movement occur at plant and storage location level. Master Data in SAP PP Master data...

What is SAP? Meaning of SAP ERP Software

  What is SAP? SAP  stands for Systems Applications and Products in Data Processing. SAP, by definition, is also the name of the ERP (Enterprise Resource Planning) software as well as the name of the company. SAP Software is a European multinational, founded in 1972 by Wellenreuther, Hopp, Hector, Plattner, and Tschira. They develop software solutions for managing business operations and customer relationships. SAP system consists of a number of fully integrated modules, which covers virtually every aspect of business management. SAP is #1 in the ERP market. As of 2010, SAP has more than 140,000 installations worldwide, over 25 industry-specific business solutions and more than 75,000 customers in 120 countries. Other Competitive products of SAP Software in the market are Oracle, Microsoft Dynamics, etc. What is SAP ERP? Why is it Required? The very fundamental question for any beginners is why Enterprise Resource Planning also called ERP, is required? To answer this, let...

SAP PP Reports Tutorial: COOIS, MB52, CS15, CS12

  There are many reports available in SAP pertaining to Master Data, Production Orders and Goods Movement against orders. It helps users to view the overall situation of the plant with ease Through PP reports, you can view Production and Consumption data about the material for the specific time period. Current Plant stock can also be displayed real time You can also see target order quantity to be executed and track the orders through various order status via standard SAP reports How to display order information systems This order info system displays the list of orders along with the quantity, dates, and their status. You can also see the goods movement on the orders. This gives view for the shop floor person to plan and execute the orders which are on priority, and you can see the actual delivered quantity against the plan. Step 1)  From SAP Easy access screen open transaction COOIS Select the option “Order Headers” in the List field Flag production orders checkbox Enter you...

SAP PP Capacity Planning: CM01, CM21

  The main function of capacity planning is to check the load at Work Center and do the capacity leveling i.e. balance the load at Work Center. It helps to calculate the production capacity based on the requirement of the product against the available capacity of the work center. MRP works with infinite capacity and creates planned orders at the Work Center at the same time since it assumes that Work Center is available all the time. So, it creates planned orders on the same date based on the requirements despite capacity shortages. You can execute those orders on that Work Center in the system which is not practically feasible in the shop floor. The main objective of the capacity leveling includes leveling overloads at Work Center and to achieve optimum utilization of Work Centers. MRP generated planned orders are converted to production orders which determine which Work Center is to be used, and accordingly the capacity requirements are generated on that Work Center. Capacity lev...